Lower Mainland System Upgrades

Vancouver to Coquitlam natural gas line upgrades

About this project

We’re upgrading our natural gas lines in Vancouver, Burnaby, Coquitlam and Surrey. These upgrades will improve the safety and reliability of our system and provide greater operational flexibility so we can best meet the current and future needs of our customers. That means if a line is impacted in one place, your gas will keep flowing to keep the heat on.

Throughout 2017, we’ll be doing a variety of pre-construction activities in Burnaby, Coquitlam and Vancouver to prepare for natural gas line construction, which will start in 2018.

Why we're replacing the gas line

We’re replacing a section of our gas line between our Coquitlam station and our East 2nd Avenue and Woodland Drive station in Vancouver because the existing line is nearing the end of its useful life. The upgrade will replace a 20-kilometre section of our existing 20-inch gas line with 30-inch gas line. Additionally, we’ll replace 300 meters of gas line in south Vancouver to provide additional seismic resilience to our natural gas system.

We’re also planning to construct approximately 97 metres of 30-inch natural gas line through a private property in the City of Vancouver west of Boundary Road.  Construction is expected to start in July 2017 and be complete by September.

Upgrading the system will ensure we’re able to meet the needs of the 210,000 customers who rely on it to deliver natural gas to their homes and businesses – now, and well into the future.

Traffic updates

Vancouver to Coquitlam map illustration

During pre-construction later in the year, you can expect some traffic delays along Broadway in Burnaby. We’ll post upcoming notifications here so you can plan your commute in advance. For specific updates on construction activities in your area, some of which may impact traffic, refer to the Updates page. We encourage you to sign-up for our newsletter, participate in upcoming public information sessions and follow us on Twitter @FortisBC for regular updates.

Construction update

Construction activities from September - December 2017

As part of our preparation work, vegetation removal is taking place in Burnaby. The majority of this work will take place along the Broadway corridor between Production Way and Underhill Avenue. Some additional vegetation will also be removed along the gas line route elsewhere in Burnaby. We’re committed to minimizing our environmental footprint and will be working with environmental consultants throughout.

We are also currently replacing the existing facility at 2nd Avenue and Woodland Drive in Vancouver. We will work with our contractors to minimize disruption to the public during this period. This work will begin in October 2017 and is anticipated to be complete in December 2018.

Safety first

Safety is our number one priority. We have rigorous plans in place to ensure the safety and security of the public, our natural gas system, the environment and our employees.

We have a comprehensive approach to safety, with regular inspections and maintenance. Our transmission and distribution pipeline system continues to have an excellent safety record, and we renew and upgrade our system in accordance with Canadian codes and standards.

Jobs and procurement opportunities

FortisBC wants to maximize the benefit of our projects in the community. Opportunities to create local jobs, opportunities for aboriginal communities and other local economic benefits always shape our approach to our projects.

If you’re interested in providing goods or services for any of our current projects, or for future opportunities, please complete the Contractors and Vendors form.

East 2nd Avenue and Woodland Drive: construction update

In preparation for natural gas line replacement, crews will be working near Woodland Station between December 11 - 20. There will be loud noise associated with this work, including a number of construction trucks in the area. Crews will be working during weekdays from 7 a.m. to 5 p.m. to minimize noise impacts and during this time, Woodland Drive will be single lane alternating traffic between East 2nd and East 3rd Avenues. Limited street parking will be available during these dates. We appreciate the public’s patience and will work to complete this project as quickly and safely as possible.

Read MoreLess

Vancouver construction work: preparation for project

We are currently working at various locations in Vancouver in advance of the project beginning in 2018. The purpose of this work is to locate underground utilities, such as waterlines, in preparation for required natural gas line upgrades. This work is scheduled to take place from November 28 to December 1, primarily at different locations along East First Avenue.

A portion of this work will take place overnight with crews working between 7 p.m. and 6 a.m., and during this time surrounding residents will likely experience noise impacts associated with the work. We apologize for the inconvenience that this causes the nearby community, and we appreciate their patience. Residents with concerns about this work can call our project phone line at 604.592.7494 or send an email to gaslineupgrades@fortisbc.com.

Read MoreLess

Coquitlam construction update: night work to prepare for project

We are currently conducting night work in the Como Lake area of Coquitlam for this gas line upgrade project. The purpose of this work is to locate underground utilities, such as waterlines, in preparation for required natural gas line upgrades. This work is being completed at night to minimize traffic impacts to the community, and to ensure its completion as quickly and safely as possible. Crews will be working between 7 p.m. and 6 a.m., and during this time surrounding residents will likely experience noise impacts associated with the work. We apologize for the inconvenience that this causes the nearby community, and we appreciate their patience. Residents with concerns about this work can call our project phone line at 604.592.7494 or send an email to gaslineupgrades@fortisbc.com.

Read MoreLess

Public information session

FortisBC representatives host an information session to discuss the upcoming vegetation clearing works taking place in Burnaby. Learn more about the work taking place.

Public information session

FortisBC representatives host an information session to discuss the upcoming vegetation clearing works taking place in Burnaby. Learn more about the work taking place.

East 1st Avenue construction update

Trenchless (underground) construction will continue until September 15 on East 1st Avenue in Vancouver between the Highway 1 off-ramp and Boundary Road. Construction will take place from 7 a.m. to 5 p.m., with one lane closed in either direction. The westbound centre lane may also be closed from 7 a.m. to 3 p.m. on a limited number of weekends.

  • Period lane closures will be required.
  • Trenchless construction will be used to minimize traffic disruptions.
  • All sidewalks, crosswalks and bus stops in the area will remain open.
East 1st Avenue Vancouver construction update

Burnaby vegetation clearing info sessions

Vegetation clearing will soon start in Burnaby as part of preparation for our Vancouver to Coquitlam natural gas line upgrades in 2018. Most of the work will be concentrated along the Broadway corridor between Production Way and Underhill Avenue, and will take place from mid-September to early November 2017.

Learn more by attending one of our two public information sessions.

Burnaby map illustration

Read MoreLess

East 1st Avenue construction update

Between July 4 and August 31, 2017, trenchless (underground) construction will occur on East 1st Avenue in Vancouver between the Highway 1 off-ramp and Boundary Road. Construction will take place from 7 a.m. to 5 p.m. from July 4 to August 31, with one lane closed in either direction. The westbound centre lane may also be closed from 7 a.m. to 3 p.m. on a limited number of weekends.

  • Period lane closures will be required.
  • Trenchless construction will be used to minimize traffic disruptions.
  • All sidewalks, crosswalks and bus stops in the area will remain open.

East 1st Ave map

Read MoreLess

Poirier and Robinson Streets construction update

We’re upgrading our natural gas line from Vancouver to Coquitlam because we’re committed to delivering natural gas safely and reliably to our customers. Our upgrade project includes replacing 20 kilometres of existing 20-inch gas line with 20 kilometres of 30-inch gas line.

Lateral work

We’ll be installing two laterals in Coquitlam in the coming weeks to prepare for construction in 2018. Laterals connect the mainline to regulator stations and lower the pressure of the natural gas before it reaches our customers. The following closures, parking restrictions and possible water service disruption will be in effect while lateral work on Poirier and Robinson Streets is underway.

Poirier and Robinson Street map

Read MoreLess

Clearing complete on right-of-way between Underhill Avenue and Production Way

We’ve completed a temporary restoration of the area around the trail. We’re committed to restoring and improving the trail and replacing invasive species with native plants. A more extensive trail restoration will be done following the installation of the new natural gas line in 2018.

The section of Burnaby Mountain Urban Trail that runs between Underhill Avenue and Production Way trail is now open—and will remain open until the summer, when further closures will be required for additional vegetation clearing activities.

Read MoreLess

Vegetation clearing on right-of-way between Underhill Avenue and Production Way

In preparation of gas line construction, we cleared vegetation along an existing right of way on Broadway, from Underhill Avenue to Production Way, in Burnaby. The clearing work is required to extend culverts on three streams along the route and to provide safe access for workers and equipment when construction begins.

Read MoreLess

Public information session

FortisBC representatives host an information session to discuss the project and answer questions about early construction activities.

Public information session

FortisBC representatives host an information session to discuss the project and answer questions about early construction activities.

Detailed engineering studies start

Upon approval from the British Columbia Utilities Commission, we created detailed studies of the precise gas line route. These studies take into account other buried utilities, like water mains. They also consider community impacts, the materials we’ll use, and construction specifications. We began procuring materials, in addition to a number of construction planning activities that are underway.

Read MoreLess

British Columbia Utilities Commission approval

Based on feedback from the public and municipalities, the proposed route is revised in April 2015, with 25 per cent of alignment re-routed based on public feedback. Six months later and with the determination made that the project is in the public interest, the British Columbia Utilities Commission grants a Certificate of Public Convenience and Necessity for the project.

Read MoreLess

Completion of early engineering studies

Early engineering studies involve preliminary designs to support an application to the British Columbia Utilities Commission. This includes studies of the general area to select a preferred route, initial designs of the pipeline and valve stations, and cost estimates to support the application.

Read MoreLess

Public information session

FortisBC representatives host an information session in Burnaby to discuss the project and answer questions.

Public information session

FortisBC representatives host an information session in Burnaby to discuss the project and answer questions. 

Public information session

FortisBC representatives host an initial information session in Vancouver to discuss the project and answer questions

Public information session

FortisBC representatives host an initial information session in Burnaby to discuss the project and answer questions.

Public information session

FortisBC representatives host an initial information session in Burnaby to discuss the project and answer questions.

Public information session

FortisBC representatives host an initial information session in Coquitlam to discuss the project and answer questions.

Keeping you informed

We’re committed to keeping the public informed about the gas line replacement project every step of the way. Over the past few years, we’ve shared information with municipalities, property owners, businesses, Aboriginal communities and residents.

We’ve held a number of information sessions to provide information about the project and the various pre-construction activities taking place in 2017. We’ll continue to communicate directly with municipalities, business owners and residents affected by the project and provide opportunities to share feedback and ask questions throughout construction.

Environmental management

Environmental consultants have been working with us at every stage of the project to help protect vegetation, fish and wildlife and their habitat. We’ve developed a comprehensive environmental management plan to protect the natural environment and qualified environmental professionals will be on site to provide environmental monitoring during construction. We are committed to working in an environmentally sensitive manner and to the highest environmental standards. Pre-construction work will be done before the bird nesting season and within the fisheries windows. 

How the Vancouver to Coquitlam Upgrade project is creating jobs and economic opportunities for BC

More than $13.2 million to date in committed local spending and significant benefits across the region.

Economic and employment benefits

socio economic benefits infographic

We want to maximize the benefits of our projects in the community. To date, $13.2 million has been spent on this project with 46 local vendors and suppliers in 10 communities, including Vancouver, Burnaby, Surrey and Richmond.

We have had involvement with vendors and suppliers from nine local communities working on the project so far, including:

  • surveyors
  • engineers
  • environmental and archaeological consultants

Business-to-business networking event

In May 2017, we held a business-to-business (B2B) networking event for attendees to learn more about the upgrade project. More than 100 local and Aboriginal business representatives from 24 natural gas line-related industries joined us at the event. Attendees networked with representatives from the project’s six shortlisted construction contractors and introduced their projects and services to the contractors.

Learn more about the event and how we build relationships within the business community.

business to business networking event
business to business networking event
business to business networking event

Get to know what we do

Meet the members of our team and learn more about the project.

Meet project manager Melanie Kilpatrick

project manager Melanie

For Melanie Kilpatrick, project manager for the Vancouver to Coquitlam gas line upgrade, some of her favourite aspects of her job include working in a team environment and helping to bring it all together. Project managers on major construction projects have traditionally been men – less than 13 per cent of all practicing engineers in Canada are women - but Melanie says FortisBC looks to provide opportunities and recognize expertise whenever possible. See our profile on Melanie.

Natural gas line safety

Our natural gas system has an excellent safety record thanks to regular inspections, maintenance and upgrades. But what does that involve? We asked Fred Young, FortisBC’s Vancouver pipeline transmission manager and a 37-year industry veteran, to tell us more. See our Q&A with Fred.

gas line sign

Investing in our local communities

We believe in supporting organizations that help build safe and caring communities within our service areas.

Partnerships within Vancouver and Coquitlam

As part of the Lower Mainland System Upgrades, we continue to raise awareness of the projects and strengthen partnerships that exist within the communities. In 2016, we invested in our local communities and provided sponsorships, including the Giro de Burnaby community event.