Menu

FortisBC projects and energy topics that matter

FortisBC projects and energy topics that matter

Project updates

Eagle Mountain - Woodfibre Gas Pipeline Project

April 4, 2025

Additional pre-construction activities along Finch Drive and Industrial Way

Starting the week of April 7, crews will return to Industrial Way and Finch Drive for approximately one week to carry out additional pre-construction activities to help further identify the locations of existing underground utilities. Construction of the new gas pipeline is tentatively planned to begin later in 2025.Work will take place between 7 a.m. - 8 p.m. Monday to Friday, and if required, Saturday 8 a.m. – 7 p.m., and will include:surveyingelectronic roadway scanningusing water pressure (hydrovac) to identify existing underground utilitiesDuring the work, single lane closures will be implemented on Industrial Way and single lane alternating traffic will be in place east of Loggers Lane on Finch Drive. We will install signage, and traffic control personnel will help to safely direct vehicles around our work zones. Access will be maintained to residences and businesses. We recognize the disruption that this may cause, and we will make efforts to reduce traffic impacts to the extent possible. We appreciate the community’s patience as we safely work to complete these activities. 
Read more

Eagle Mountain - Woodfibre Gas Pipeline Project

March 31, 2025

Update on construction near Valleycliffe and in the Ray Basin area

Preparation activities at our temporary construction laydown yard northeast of Valleycliffe are now expected to begin on April 7. See our March 18 update below for more details. Similar vegetation and tree clearing activities will continue northwest along the new right of way towards town as construction continues into 2025.In addition, beginning as early as the week of April 7, crews will start heli-logging in the Ray Basin area.Clearing will generally occur from 7 a.m. - 8 p.m. Monday to Friday and 8 a.m. - 7 p.m. Saturdays.For safety, minor traffic delays on the Mamquam Forest Service Road may occur and the area will be monitored by traffic control personnel.We appreciate your patience as we safely complete these activities.
Read more

Eagle Mountain - Woodfibre Gas Pipeline Project

March 18, 2025

Update on temporary construction laydown yard near Valleycliffe

We’ve been working closely with the District of Squamish as we move forward with a temporary construction laydown yard northeast of Valleycliffe, which we plan to begin preparing in late March. This follows the District of Squamish Council decision in fall 2024 to approve a Temporary Use Permit for the yard, and issuance of the permit this month. The construction laydown yard will be used for storing equipment and materials, as well as parking and fuelling. These activities reflect a reduction in uses from our initial plans. In particular, we no longer intend to use an approximately 2.5 acre portion of land on the west side of the approved area, reducing the number of trees to be cleared, nor will we use site offices as originally planned. The yard’s location was selected in consultation with Skwxwú7mesh Úxwumixw (Squamish Nation), whose land we are leasing for the yard. Beginning in late March crews will be undertaking vegetation and tree clearing at the temporary construction laydown yard, as well as along our new right of way.The new temporary construction laydown yard will be located near the intersection of Mamquam River Forest Service Road and Powerhouse Springs Road.Clearing works will generally occur from 7 a.m. - 8 p.m. Monday to Friday and 8 a.m. - 7 p.m. Saturdays.There will be trail closures in this area, including the Connector Trail north of the construction laydown yard. Closed areas are highlighted in yellow on the map below.Minor traffic delays on the nearby Forest Service Roads may occur to accommodate large trucks and the area will be monitored by traffic control personnel.We’ve notified nearby residents and local recreational groups to help bring awareness to this work and inform their trail-use planning. For safety and awareness, we’ll also be posting trail closure signage.Thank you for your patience, as we complete this work safely, and as quickly as possible. 
Read more