Sorry, you need to enable JavaScript to visit this website.
Menu

FortisBC projects and energy topics that matter

FortisBC projects and energy topics that matter

Image
Building legacy through leadership: Cody La Rock
Featured story
FortisBC is committed to partnering with local Indigenous businesses. Discover how our partnership with Indigenous Iron is contributing to the Eagle Mountain – Woodfibre Gas Pipeline Project.

Project updates

Eagle Mountain - Woodfibre Gas Pipeline Project

August 31, 2026

Upcoming traffic impacts in Squamish

Beginning August 31, crews will be working at the intersection of Highway 99 and Industrial Way to remove survey equipment. The work is only anticipated to require one or two evenings, but intermittent lane closures may be in place until September 3.Work will be taking place overnight between 6:30 p.m. – 6:30 a.m.Intermittent lane closures will be in place, and traffic control personnel will be onsite to help road users navigate around construction.Thank you for your patience as we complete this work safely, and as quickly as possible. If you have any questions about this work, we encourage you to reach out to the FortisBC team at [email protected] or 1-855-380-5784.
Read more

Eagle Mountain - Woodfibre Gas Pipeline Project

August 28, 2026

Squamish construction update

Construction activities continue to advance along Finch Drive. As communicated on August 21, this includes work in the section that is currently closed between Highway 99 and Loggers Lane, and near the eastern end of Finch Drive.Finch Drive between Highway 99 and Loggers LaneSheet piling is ongoing and expected to be complete next week.Once sheet piling is complete, crews will transition to pipeline installation.The road closure is anticipated to remain in place until October.Eastern end of Finch DriveSheet piling at the eastern end of Finch Drive is expected to begin as early as tomorrow, August 29, and continue for approximately five days.Following completion of sheet piling, crews will transition to pipeline installation in this area. Pipeline installation and remaining work in these areas are expected to continue through October.Sheet piling along Finch Drive will generally occur between 7 a.m. and 8 p.m., Monday through Friday; 8 a.m. and 7 p.m. on Saturdays; and 10 a.m. and 4 p.m. on Sundays. Please note that lower-noise activities associated with pipeline activities may occur outside of these hours, and equipment such as generators and pumps may be required to operate overnight.We appreciate the community's patience as we safely complete these activities. For questions about this work, please contact the FortisBC team at [email protected] or 1-855-380-5784. You can also sign up for our email newsletter for the latest construction updates.
Read more

Eagle Mountain - Woodfibre Gas Pipeline Project

August 21, 2026

Squamish construction update

Construction activities continue to advance along Finch Drive. Work is focused in the section currently closed between Highway 99 and Loggers Lane, and in the private property at 1039 Finch Drive.Finch Drive between Highway 99 and Loggers LaneSheet piling is ongoing and expected to continue into early September.Once sheet piling is complete, crews will transition to pipeline installation.The road closure is anticipated to remain in place until October.Eastern end of Finch DriveCrews continue to work in the private property at 1039 Finch Drive.To prioritize construction activities between Highway 99 and Loggers Lane and in 1039 Finch Drive, sheet piling at the eastern end of Finch Drive was deferred and is now expected to begin in the middle to latter part of the week of August 24. The sheet piling in this area is anticipated to take approximately five days to complete.Hydrovac activities will also be required and are expected to begin as early as Saturday, August 22.Sheet piling and hydrovac activities along Finch Drive will occur between 7:00 a.m. and 8:00 p.m. Monday to Friday, as well as Saturdays 8:00 a.m. to 7:00 p.m. and Sundays 10:00 a.m. to 4:00 p.m. Please note that lower-noise activities associated with pipeline activities may occur outside of these hours, and equipment such as generators and pumps may be required to operate overnight.We appreciate the community's patience as we safely complete these activities. For questions about this work, please contact the FortisBC team at [email protected] or 1-855-380-5784. You can also sign up for our email newsletter for the latest construction updates.
Read more